| The University of Massachusetts at Boston has long occupied
an area in the city called Columbia Point, site of several housing projects and
the University. While Boston is essentially built on landfill - soil and rock
was brought in from the west and south of the city in the 1800's to fill in the
large tidal basin of salt marshes and fens that form the land we know today, some
areas were used as dumping grounds for the city's trash. One of the areas was
Columbia Point, which was used as a dump from 1940 - 1960. While the trash settled
and gave off its characteristic smell, it eventually settled and digested enough
to allow building on the site.
Almost all large buildings in Boston are
founded on piles - long concrete, steel or wood (in the old building) posts that
are driven into the clays underlying the landscape to support the weight of each
building. These piles were essential, as the saturated landfill underlying much
of the city simply cannot support the weight of a building on its own. The buildings
at Columbia Point were constructed on piles so that further settlement of the
underlying trash would not affect the stability of the building.
The first
buildings constructed at the University of Massachusetts campus some 20 years
ago had unprotected slabs, as it was assumed that the trash had become benign
and had ceased to produce noxious gasses. This turned out not to be the case,
not just with these buildings, but with many buildings built on former dumps in
the Boston area. These buildings were classified as "sick" buildings, with inhabitants
complaining of respiratory and other physical distress. Additionally, it was discovered
that the gasses from the landfills actually degraded the concrete and reinforcing
steel in the slabs that sat directly over the underlying soils.
Because
of the settlement of the trash under these buildings, it was proving difficult
to provide some type of protection for the concrete and the building itself…some
sort of barrier system that would not allow the gasses to penetrate into the slab
yet be able to withstand the settlement of the very soils that would support such
a barrier.
With the advent of concrete protective liners (CPL), at least
the problem of providing something that would remain attached to the underside
of the slab was solved. CPL's have integral anchors that lock into the concrete
securely and completely, and so the settlement issue was addressed.
When the New Campus Center was being designed, the Architect on the project,
Kallman McKinnell and Wood (KMW) hired Haley and Aldrich (H&A), one of Boston's
premier geotechnical consulting firms, to address several issues, among which was
the barrier system which was to be integrated into the walls and slabs of the
building. H&A provided a design that not only recognized the complexity of the
building foundation and the 200+ pile caps upon which the building sat, but also
the intent that the system be constructible with a minimum amount of
inconvenience and time delays to the General Contractor and other trades.
After the project was bid it was discovered that the low bidder on the membrane
portion of the project had neither the experience nor the expertise in all aspects of deploying,
detailing and welding such a membrane system or its interface with the various
coatings used in the subgrade structure. While the bidder,
Premier Caulking of Derry, New Hampshire, had years of experience in waterproofing
membranes, nothing they had done even remotely resembled the GSE StudLiner system
chosen for gas membrane application or the work required to interface liquid
applied membranes with roll produced membrane systems. As part of the
qualification package, Resicon USA was included as the training and testing
authority approved by GSE and the State of Massachusetts for the StudLiner
and the coating system. Resicon personnel spent the next several months
working with the subcontractor, the General Contractor, Suffolk Construction,
the architect, the engineers and the State of Massachusetts to detail and
implement first the pile cap and wall membrane applications, then the body
of the project, which sealed the lower level of the entire building.
Resicon provided qualified independent personnel, and trained and
certified Premier's personnel on all aspects of welding, detailing
and testing the membranes and coatings that were applied. Because
of the urgent nature of the work, all training was done on the site
during the actual application of the system. Resicon USA also provided
on-the-fly design and construction advice to all parties involved in
the project which kept the membrane system installation on schedule.
| |
 | | StudLiner
membrane being installed under building | |